ANALYSIS OF
RETURN ON INVESTMENT ASSOCIATED WITH CHANGES IN OPERATIONAL TIME IN THE
CONSTRUCTION OF THE SIGLI-BANDA ACEH TOLL ROAD
I Made Bayu
Anggara1, Yusria Darma2, Mubarak3�
Universitas Syah Kuala, Banda Aceh, Indonesia
[email protected]1, [email protected]2,
[email protected]3
![]()
ABSTRACT
The problem with this research is that the
government was late in land acquisition, so that PT. Hutama Karya (Persero) as
the concession holder in the implementation of toll road construction is
constrained in a number of locations. This study aims to determine the impact
of delays in land acquisition and implementation of the construction of the
Sigli-Banda Aceh Toll Road on net profit and return on investment at the end of
the concession period. This study uses a quantitative method approach. Data
analysis techniques use Present Net Value (NPV), Internal Rate of Return (IRR),
and sensitivity analysis. The results of the study show that delays of 1, 2, and
3 years have an impact on concessionaires going through cash flow deficit
periods of 17, 19, and 20 years and surplus cash flow periods of 23, 21, and 20
years. year, where investment returns occur in the 32nd (2050), 34th (2052) and
36th (2054) years, so that at the end of the concession period, the net profit
that can be achieved by the concession holder is with an NPV value of Rp.
9,162,336,077,086, Rp. 6,858,784,951,438 and Rp. 4,680,164,756,915. If there
are no delays, then the concessionaire only needs to go through a cash flow
deficit period of 16 years and a cash flow surplus period of 24 years, where
the return on investment capital occurs in year 30 (2048), so that the net profit that can be obtained by the concessionaire is
with an NPV value of Rp. 11,647,590,651,181.
Keywords: land
acquisition, construction implementation, concession, return on investment,
toll road.
![]()
Corresponding Author: Yusria Darma
E-mail: [email protected]
INTRODUCTION
The Sigli�Banda Aceh Toll Road is part of the Trans
Sumatra Toll Road (JTTS), which spans 74.1 km and is divided into six sections.
Section 1 is Padang Tiji�Seulimeum, with a length of 24.3 km. Section 2 is
Seulimeum�Jantho, with a length of 7.6 km. Section 3, namely Jantho�Indrapuri,
is 16 km long. Section 4, namely Indrapuri�Blang Bintang, 13.5 km long. Section
5 is Blang Bintang�Kutabaro with a length of 7.7 km. Section 6, Kutabaro�
Baitussalam along 5 km (Rani & Azlan,
2020). The investment value for the construction of the
Sigli-Banda Aceh Toll Road is Rp. 12,533,551,000,000, using the BUMN assignment
funding scheme. Plans to start construction in 2019 and plan to start operations in 2022.
The status of the Sigli�Banda Aceh Toll Road project is still operating (Winodya, 2021).
Presidential Regulation of the
Republic of Indonesia Number 100 of 2014 Concerning the Acceleration of Toll
Road Development in Sumatra states that the Government assigned PT to
accelerate toll road construction. Hutama Karya (Persero). The Minister of
Public Works granted toll road concession rights to PT. Hutama Karya (Persero)
for 40 years covering funding, technical planning, construction, operation, and
maintenance (Riyanto & Joesoef, 2020). The concession period of 40
years is expected that the company will have enough time to recover the
invested capital and get an appropriate return.
Since the Sigli�Banda Aceh
Toll Road project is a development for the public interest, the land
acquisition must be carried out by the Government (Silalahi,
2022). The problem in this research
is that the Government was late in procuring land for the Sigli�Banda Aceh Toll
Road (Al Mukahfi,
2020). The problem of delays was
also reported by several online print media. The Government's delay in the land
acquisition was caused by compensation issues (Wardana,
2021). Other delays were caused by
administrative constraints between agencies, which were a little slow, which
affected official activities and the legal status of the court as the basis for
executors for land use (Muna, 2022). In addition, at the toll
road construction site, there are also several unknown burial points, requiring
a relocation policy and having consequences for the budget (Zairi, 2020).
Delays in land acquisition by the Government caused
PT. Hutama Karya (Persero), as the concessionaire (permit holder) in the
construction of the Sigli-Banda Aceh Toll Road, was constrained at several
locations. The Sigli-Banda Aceh Toll Road construction only runs smoothly in
locations with clear and clean clearance. Delays in land acquisition and
construction implementation can impact net profit and return on investment at
the end of the concession period (Kusuma, 2017). Based on the background above, this research aims to
analyze the return on investment associated with changes in operational time
for the construction of the Sigli-Banda Aceh toll road.
METHODS
This research uses a quantitative
method approach. Quantitative methods are methods whose output is in the form
of numbers.� In connection with this
research related to financial analysis, the type of data used is only secondary
data. Secondary data is data obtained or collected by researchers from existing
sources. The secondary data used in this study are as follows:
1.
Net Present
Value (NPV)
NPV is used to determine the feasibility of investing in the
construction of the Sigli-Banda Aceh Toll Road based on the net profit obtained
at the end of the concession period. The NPV formula can be seen in Equation
(1).
NPV ����������� =
��
Where:
NPV ����������� = Net
Present Value (in rupiah)
Ct �������������� = cash flow
per year in period t
C0 �������������� =
Initial investment value in year 0 (in rupiah)
R ���������������� =
Interest rate or discount rate (in %)
NPV >
0, indicating that the investment in the construction of the Sigli-Banda Aceh
Toll Road is profitable and feasible. NPV < 0, indicating that investment in
the construction of the Sigli-Banda Aceh Toll Road is a loss and not feasible.
NPV = 0, indicating that the investment in the construction of the Sigli-Banda
Aceh Toll Road has neither profit nor loss, so it has no feasibility value.
2.
Sensitivity analysis
Sensitivity analysis was used to determine
the impact of delays in land acquisition and construction implementation on the
concession period for the construction of the Sigli-Banda Aceh Toll Road (Hatmoko & Kistiani,
2017). Sensitivity analysis was carried out in
3 scenarios, namely delay simulations ranging from 1-3 years. The sensitivity analysis steps can be
described as follows:
a. Projecting an increase in toll road
revenues and value-added tax for all gates with a simulated one-year delay
starting from 2021�2058, a two-year delay starting from 2022�2058, and a
three-year delay starting from 2023�2058.
b. Projecting business entity costs from 2019�2058 for each of the
one-year, two-year, and three-year delay simulations.
c. Calculate the NPV using Equation (1) for each of the one-year,
two-year, and three-year delay simulations.
d. Calculate the IRR using Equation (2) for each of the one-year,
two-year, and three-year delay simulations.
RESULTS AND DISCUSSION
1. Projection of Increase in Toll Road Fares Based on Inflation Rate
The increase in toll road tariffs in 5 years is
projected using the tariff price in the previous year multiplied by the
inflation rate of 2.93%, then added back to the tariff price in the previous
year.
Table 1. Projected Increase in Tariff Prices
|
class |
Tariff
Price (IDR.
/Km) |
Projection
of Toll Road Price Increase Based on Inflation
Rate 2.93% per 5 Years (Rp. /Km) |
|||
|
2020�2027 |
2028�2032 |
2033
� 2037 |
2038
� 2042 |
||
|
Group I |
1,191 |
1,191 |
1,226 |
1,262 |
1,299 |
|
Group II |
1,787 |
1,787 |
1839 |
1893 |
1949 |
|
Group III |
1,787 |
1,787 |
1839 |
1893 |
1949 |
|
Group IV |
2,382 |
2,382 |
2,452 |
2,524 |
2,598 |
|
Group V |
2,382 |
2,382 |
2,452 |
2,524 |
2,598 |
|
class |
Tariff
Price (IDR.
/Km) |
Projection
of Toll Road Price Increase Based on Inflation
Rate 2.93% per 5 Years (Rp. /Km) |
|||
|
2043
� 2047 |
2048
� 2052 |
2053
� 2057 |
2058 |
||
|
Group I |
1,191 |
1,337 |
1,376 |
1,416 |
1,458 |
|
Group II |
1,787 |
2006 |
2065 |
2.125 |
2,187 |
|
Group III |
1,787 |
2006 |
2065 |
2.125 |
2,187 |
|
Group IV |
2,382 |
2,674 |
2,752 |
2,833 |
2,916 |
|
Group V |
2,382 |
2,674 |
2,752 |
2,833 |
2,916 |
Table 1 shows that the increase in
toll road fares per km for each class every five years is insignificant. This is based on data from Bank Indonesia
(2022), the average inflation rate in the five years (August 2017�July 2022)
reached 2.93%. Class I for the first year or period of operation has a tariff
of Rp. 1,191/km, and the last year, the concession period was Rp. 1,458/km.
Classes II and III have an Rp tariff for the first year or operation period.
1,787/km, and the last year, the concession period was Rp. 2,187/km. Classes IV
and V for the first year or period of operation have a tariff of Rp. 2,382/km
and the last year the concession period was Rp. 2,916/km.
Several
previous studies also experienced a flat inflation rate. The flat inflation
rate on the Serpong�Cinere Toll Road is set at 3.21% once every three years for
a concession period of 35 years (Aulia & Buana, 2020). The flat inflation rate on the
Pandaan�Malang Toll Road is set at 4.86% once every three years for a
concession period of 35 years (Sari & Widyastuti,
2019). The flat inflation rate on the
Mengwi�Gilimanuk Toll Road is set at 3.09% once every five years for a
concession period of 32 years (Krisnananda &
Kartika, 2021).
2.
Projection of
Increase in Toll Road Traffic Volume Based on Vehicle Growth Rate in the
Sumatra Islands
The increase in traffic volume in the second
to last year of the concession period is projected by employing the previous
year's traffic volume multiplied by the growth rate of vehicles in the Sumatran
Archipelago of 4.54%, then added back to the previous year's traffic volume.
1) The traffic volume at
the Padang Tiji Gate for the first year of operation (2024) is planned to be
5,504,666 vehicles and in 2058 there will be 24,907,826 vehicles.
2) The traffic volume at
the Seulimeum Gate for the first year of operation (2022) is planned to be
80,596 vehicles, and in 2058, there will be 6,624,118 vehicles.
3) The traffic volume at
the Jantho Gate for the first year of operation (2020) is planned to be 1,900
vehicles, and in 2058, there will be 3,243,783 vehicles.
4) The traffic volume at
the Indrapuri Gate for the first year of operation (2020) is planned to be
85,699 vehicles, and in 2058, there will be 3,662,868 vehicles.
5) The traffic volume at
the Blang Bintang Gate for the first year of operation (2020) is planned to be
69,646 vehicles, and in 2058, there will be 4,459,195 vehicles.
6) The traffic volume at
the Kuta Baro Gate for the first year of operation (2023) is planned to be
1,817,179 vehicles, and in 2058, there will be 12,366,103 vehicles.
7) The traffic volume at
the Baitussalam Gate for the first year of operation (2023) is planned to be
1,044,350 vehicles, and in 2058, there will be 7,221,004 vehicles.
3.
Cross
The increase in toll road revenue in the
first year to the last year of the concession period is projected by the fare
price multiplied by the segment's length, then by the traffic volume for each
year. After a year of operation, the traffic volume increases by 4.54% every
following year, and within five years, the fare price increases by 2.93%.
1) Toll road revenue at
the Padang Tiji Gate for the first year of operation (2024) is Rp.
505,535,649,613, and in 2058 Rp. 2,799,951,135,437.
2) Toll road revenue at
the Seulimeum Gate for the first year of operation (2022) is Rp. 2,998,298,012,
and in 2058 Rp. 399,094,870,444.
3) Toll road revenue at
the Jantho Gate for the first year of operation (2020) was Rp. 39,389,368, and
in 2058, Rp. 217,753,368,496.
4) Toll road revenue at the
Indrapuri Gate for the first year of operation (2020) was Rp. 1,452,660,221,
and in 2058 Rp. 285,752,360,438.
5) Toll road revenue at
the Blang Bintang Gate for the first year of operation (2020) was Rp.
1,221,550,560, and in 2058 Rp. 316,980,225,651.
6) Toll road revenue at
the Kuta Baro Gate for the first year of operation (2023) is Rp.
79,971,981,987, and in 2058, Rp. 1,013,047,994,057.
7) The toll road revenue
at the Baitussalam Gate for the first year of operation was Rp. 56,401,170,271,
and in 2058, Rp. 681,666,790,325.
4.
Projection of
Value-Added Tax (VAT)
Before 2022, the toll road VAT rate is 10%. This is based on the
Regulation of the Director General of Taxes Number PER�10/PJ/2015. From 2022 to
2024, the toll road VAT rate will be charged at 11%, while in 2025, until an
undetermined year, the toll road VAT rate will be charged at 12%. This is based
on the Law of the Republic of Indonesia Number 7 of 2021.
VAT for toll roads in the first year to the last year of the concession
period is projected using all gates' total toll road revenue multiplied by 10%,
11%, and 12%. All gates' total toll
road revenue for the first year of operation was Rp. 2,713,600,149 with VAT of
Rp. 271,360,015. In the last year of the concession period, all gates' total
toll road revenue was Rp. 5,714,246,744,848 with VAT of Rp. 685,709,609,382.
5.
Projection of
Salary Increase for Toll Road Operational Employees Based on Inflation Rate
The Sigli�Banda Aceh Toll Road operational staff includes 125 field
employees, eight officers, four supervisors, and one manager. PT. Hutama Karya (Persero), in 2020, has set a salary/per month for field
employees of Rp. 3,500,000, officers Rp. 7,000,000, supervisor Rp. 10,000,000,
and a manager of Rp. 20,000,000. The salary for toll road operational employees
in the first year is calculated by multiplying the employee's salary/month by
the number of months in a year, then multiplying by the number of employees
again. The increase in toll
road operational employee salaries in the second to last year of the concession
period is projected using the previous year's employee salaries multiplied by
the inflation rate of 2.93%, then added back to the previous year's employee
salaries. In this case, the salary for toll road operational employees in the
first year of operation (2020) is Rp. 6,642,000,000, and in 2058, Rp.
19,901,867,785.
6.
Business
Entity Cost Projection
PT. Hutama Karya (Persero) includes toll road expenses and revenues. Toll
road expenses are several costs incurred by business entities which include construction
costs, maintenance costs (routine maintenance, periodic maintenance 2, 3, 4, 5,
10, and 15 years), salaries of toll road operational employees, VAT, Income Tax
article 21, PBB, as well as administrative and general costs. Business entity costs in the first year to the last year of the
concession period, are projected by means of total toll road expenditures
reduced by total toll road revenues (Nurida, 2018).
The Sigli�Banda Aceh Toll Road construction in 2019 was a year of
expenses without income. In 2019 the total toll road expenditure was Rp.
1,577,344,986,004, with the remaining toll road revenue of Rp.
-1,577,344,986,004. This is because, in 2019, it is still in the commencement
stage of toll road construction. The years 2020�2058 have shown toll road
revenues. This revenue is obtained from the operation of toll roads at several
gates within a certain period and the operation of toll roads at all gates
within a certain period. In 2058 the total toll road expenditure is Rp. 1,987,560,339,673,
the total toll road revenue is 5,714,246,744,848, with the remaining toll road
revenue of Rp. 3,726,686,405,175.
7.
Net Present
Value (NPV)
A delay in land acquisition and toll road construction can impact the
period of cash flow deficit and surplus cash flow. The longer the delay, the
longer the period of cash flow deficit, which will then be followed by a
shorter period of surplus cash flow. The impact of the delay from the two cash
flow periods can then have implications for the net profit received by the
concessionaire at the end of the concession period (RARA, 2022). Net profit is the
difference between the total cash flow and the initial investment value of Rp.
12,533,551,000,000. Net profit is representative of the NPV value.
If there are no delays, land acquisition and construction of the
Sigli-Banda Aceh Toll Road will not impact the cash flow deficit period and the
surplus cash flow period. The period of cash flow deficit starts from year 1 to
year 16 (2019�2034) for 16 years. The surplus cash flow period starts from year
17 to year 40 (2035�2058) for 24 years. This can be seen in Figure 1.

Figure
1. Period of Devisit and Surplus Cash Flows If There Are No Delays in
Land
Acquisition and Toll Road Construction Implementation
The concessionaire begins to receive a cash flow surplus in the 17th year
(2035) of Rp. 497,137,778,131. In the 30th year period (2048), the
concessionaire has received a return-on-investment capital of Rp.
12,582,481,312,811. In the 40th year (2058), the concessionaire can target a
total cash flow of Rp. 24,181,141,651,181. Based on the total cash flow, the
concessionaire's net profit (NPV) is Rp. 11,647,590,651,181. In this case, the
impact of delays is simulated starting from 1-3 years through a sensitivity
analysis previously analyzed with NPV.
The impact of a 1-year delay is the impact that arises from the
incomplete completion of land acquisition in 2020 so that it will continue in
2021. The impact of a 1-year delay on the cash flow period of deficit and
surplus can be seen in Figure 2.

Figure 2. The
Impact of 1 Year Delay on the Deficit and Surplus Cash Flow Periods
Figure 2 shows that the cash flow deficit period starts from year 1 to
year 17 (2019�2035) for 17 years. The surplus cash flow period starts from year
18 to year 40 (2036�2058) for 23 years. This shows that the delay of 1 year has
impacted the concessionaire to go through a cash flow deficit period of 17
years and a cash flow surplus of 23 years. The concessionaire begins to receive
a cash flow surplus in the 18th year (2036) of Rp. 207,187,476,947. In the 32nd
year (2050), the concessionaire received an Rp return on investment capital.
12,821,917,349,413. In the 40th year (2058), the concessionaires can only
target a total cash flow of IDR 21,695,887,077,086. Based on the total cash
flow, the concessionaire's net profit (NPV) is Rp. 9,162,336,077,086. The
impact of delays in land acquisition and the implementation of toll road
construction during this one year can still provide investment feasibility for
concessionaires.
The impact of the 2-year delay is the impact that arises from the
incomplete completion of land acquisition in 2020, so it will continue in 2022.
The impact of the 2-year delay on the cash flow period of deficit and surplus
can be seen in Figure 3.

Figure
3. The Impact of a 2-Year Delay on the Deficit and Surplus Cash Flow Periods
�����
Figure 3 shows that the cash flow deficit period starts from year 1 to
year 19 (2019�2037) for 19 years. The surplus cash flow period starts from year
20 to year 40 (2038�2058) for 21 years. This shows that the two-year delay has
impacted the concessionaire through 19 years of deficit cash flow periods and
21 years of surplus cash flow periods. The concessionaire begins to receive a
cash flow surplus in the 20th year (2038) of Rp. 581,285,329,583. In the 34th
year (2052), the concessionaire received a return-on-investment capital of Rp.
12,798,308,196,344. In the 40th year (2058), the concessionaires can only
target a total cash flow of IDR 19,392,335,951,438. Based on the total cash
flow, the concessionaire's net profit (NPV) is Rp. 6,858,784,951,438. The
impact of land acquisition and toll road construction delays for the past 2
years can still provide investment feasibility for concessionaires.
The 3-year delay is
the impact that arises from the incomplete land acquisition in 2020, so it will
continue in 2023. The impact of the 3-year delay on the cash flow period of
deficit and surplus can be seen in Figure 4.

Figure
4. The Impact of 3 Years Delay on the Period of Devisit and Surplus Cash Flows
Figure 4 shows that the cash flow deficit period starts from year 1 to
year 20 (2019�2038) for 20 years. The surplus cash flow period starts from year
21 to year 40 (2039�2058) for 20 years. This shows that the 3-year delay has
had an impact on the concessionaire going through a 20-year period of deficit
cash flows and a 20-year period of surplus cash flows. The concessionaire
begins to receive a cash flow surplus in the 21st year (2039) of Rp.
97,905,635,695. In the 36th year (2054), the concessionaire received a return-on-investment
capital of Rp. 13,214,732,039,248. In the 40th year (2058), the concessionaires
can only target a total cash flow of Rp. 17,213,715,756,915. Based on the total
cash flow, the concessionaire's net profit (NPV) is Rp. 4,680,164,756,915. The
impact of land acquisition and toll road construction delays for the past three
years can still provide concessionaires with investment feasibility.
CONCLUSION
Delays in land
acquisition and the construction of the Sigli�Banda Aceh Toll Road for 1, 2,
and 3 years had an impact on the concessionaires going through periods of cash
deficit cash flows of 17, 19, and 20 years and periods of surplus cash flows of
23, 21, and 20 year, where the return on investment capital occurs in the 32nd
(2050), 34th (2052), and 36th (2054) years, so that at the end of the concession
period, the net profit that the concessionaire can achieve is the NPV value Rp.
9,162,336,077,086, Rp. 6,858,784,951,438, and Rp. 4,680,164,756,915. Suppose
there are no delays in land acquisition and construction of the Sigli�Banda
Aceh Toll Road. In that case, the concessionaire only needs to go through a
cash flow deficit period of 16 years and a cash flow surplus period of 24
years, whereby the return on investment capital occurs in the 30th year (2048)
so that at the end of the concession period, the net profit that can be
achieved by the concessionaire is with an NPV value of Rp. 11,647,590,651,181. The
implication of this study is that delays in land acquisition and construction
implementation can have an impact on net profits and return on investment at
the end of the concession period. It is recommended that researchers can then
review the strategy of accelerating land acquisition in toll road projects, so
that it can become a reference material for the Government.
REFERENCES
Al Mukahfi, S. (2020). Mekanisme Pelaksanaan Pengadaan
Tanah Jalan Tol Sigli-Banda Aceh di Kecamatan Blang Bintang Kabupaten Aceh
Besar (Analisis Kelayakan Ganti Rugi Menurut Undang-Undang Nomor 2 Tahun 2012
Tentang Pengadaan Tanah Bagi Pembangunan Untuk Kepentingan Umum). UIN
Ar-Raniry Banda Aceh.
Aulia, W., & Buana, C. (2020). Studi Kelayakan Jalan Tol
Serpong-Cinere Ditinjau dari Segi Ekonomi dan Finansial. Jurnal Teknik ITS,
8(2), E154�E159. 10.12962/j23373539.v8i2.48066
Hatmoko, J. U. D., & Kistiani, F. (2017). Model Simulasi
Risiko Rantai Pasok Material Proyek Konstruksi Gedung. Media Komunikasi
Teknik Sipil, 23(1), 1�13. https://doi.org/10.14710/mkts.v23i1.14697
Krisnananda, J., & Kartika, A. A. G. (2021). Analisis
Kelayakan Ekonomi dan Finansial Pembangunan Jalan Tol Mengwi-Gilimanuk. Jurnal
Teknik ITS, 10(2), E253�E258. 10.12962/j23373539.v10i2.69868
Kusuma, S. C. (2017). Analisis Dampak Keterlambatan Pengadaan
Tanah Dan Pelaksanaan Konstruksi Terhadap Masa Konsesi Pada Pembangunan Jalan
Tol Kertosono-Mojokerto. Institut Teknologi Sepuluh Nopember.
Muna, K. S. (2022). Tinjauan Undang-Undang Nomoar 41 Tahun
2004 Terhadap Tanah Wakaf Terdampak Jalan Tol (Studi Kasus di Desa Baderan
Kecamatan Geneng Kabupaten Ngawi). IAIN Ponorogo.
Nurida, M. A. (2018). Identifikasi Dampak Sosial Ekonomi
Terhadap Masyarakat Akibat Pembanguanan Jalan Tol Pekanbaru-Dumai.
Universitas Islam Riau.
Rani, H. A., & Azlan, M. (2020). Dampak Pembangunan Jalan
Tol Banda Aceh-Sigli Terhadap Lingkungan. Tameh: Journal of Civil
Engineering, 9(1), 11�21. https://doi.org/10.37598/tameh.v9i1.100
Rara, R. (2022). Analisis Fiqih Siyasah Tentang Mekanisme
Ganti Rugi Hak Milik Atas Tanah Dalam Undang-Undang No 2 Tahun 2012 Tentang
Pengadaan Tanah Bagi Pembangunan Untuk Kepentingan Umum (Studi Pada Pembangunan
BendunganTiga Dihaji Kabupaten OKU Selatan). Universitas Islam Negeri Raden
Intan Lampung.
Riyanto, A., & Joesoef, I. E. (2020). Penugasan Badan
Usaha Milik Negara Dalam Pengusahaan Jalan Tol: Studi Penugasan PT. Hutama
Karya (Persero) Dalam Pengusahaan Jalan Tol Di Sumatera. National Conference
on Law Studies (NCOLS), 2(1), 344�379.
Sari, N. F. A., & Widyastuti, H. (2019). Analisis
kelayakan ekonomi dan finansial pembangunan jalan tol Pandaan-Malang. Jurnal
Teknik ITS, 8(1), E13�E19. 10.12962/j23373539.v8i1.41495
Silalahi, R. N. (2022). Tinjauan Yuridis Proses Pemberian
Ganti Kerugian Pengadaan Tanah Bagi Pembangunan untuk Kepentingan Umum dalam
Pembangunan Pelabuhan Terminal Multipurpose Kuala Tanjung di Kabupaten Batubara.
Universitas Medan Area. https://doi.org/10.34007/jehss.v5i2.1412
Wardana, R. Y. (2021). Masalah Ganti Rugi Lahan Masih Jadi
Momok Pembangunan Jalan Tol Sibanceh Seksi 1, Warga Layangkan Protes.
Gridoto.Com.
Winodya, V. (2021). Peran Media Sosial Instagram@ Jokowi
Dalam Komunikasi Politik Presiden Joko Widodo Saat Peresmian Jalan Tol.
Universitas Katholik Soegijapranata Semarang.
Zairi, M. B. (2020). Pembangunan Jalan Tol Sibanceh Masih
Terkendala Pembebasan La-han, Pemerintah Aceh Gelar Rakor.