Analysis of Return on Investment Associated with Changes in Operational Time in the Construction of the Sigli-Banda Aceh Toll Road
DOI:
https://doi.org/10.58344/jws.v2i2.222Keywords:
land acquisition, construction implementation, concession, return on investment, toll roadAbstract
The problem with this research is that the government was late in land acquisition, so that PT. Hutama Karya (Persero) as the concession holder in the implementation of toll road construction is constrained in a number of locations. This study aims to determine the impact of delays in land acquisition and implementation of the construction of the Sigli-Banda Aceh Toll Road on net profit and return on investment at the end of the concession period. This study uses a quantitative method approach. Data analysis techniques use Present Net Value (NPV), Internal Rate of Return (IRR), and sensitivity analysis. The results of the study show that delays of 1, 2, and 3 years have an impact on concessionaires going through cash flow deficit periods of 17, 19, and 20 years and surplus cash flow periods of 23, 21, and 20 years. year, where investment returns occur in the 32nd (2050), 34th (2052) and 36th (2054) years, so that at the end of the concession period, the net profit that can be achieved by the concession holder is with an NPV value of Rp. 9,162,336,077,086, Rp. 6,858,784,951,438 and Rp. 4,680,164,756,915. If there are no delays, then the concessionaire only needs to go through a cash flow deficit period of 16 years and a cash flow surplus period of 24 years, where the return on investment capital occurs in year 30 (2048), so that the net profit that can be obtained by the concessionaire is with an NPV value of Rp. 11,647,590,651,181.
References
Al Mukahfi, S. (2020). Mekanisme Pelaksanaan Pengadaan Tanah Jalan Tol Sigli-Banda Aceh di Kecamatan Blang Bintang Kabupaten Aceh Besar (Analisis Kelayakan Ganti Rugi Menurut Undang-Undang Nomor 2 Tahun 2012 Tentang Pengadaan Tanah Bagi Pembangunan Untuk Kepentingan Umum). UIN Ar-Raniry Banda Aceh.
Aulia, W., & Buana, C. (2020). Studi Kelayakan Jalan Tol Serpong-Cinere Ditinjau dari Segi Ekonomi dan Finansial. Jurnal Teknik ITS, 8(2), E154–E159. 10.12962/j23373539.v8i2.48066
Hatmoko, J. U. D., & Kistiani, F. (2017). Model Simulasi Risiko Rantai Pasok Material Proyek Konstruksi Gedung. Media Komunikasi Teknik Sipil, 23(1), 1–13. https://doi.org/10.14710/mkts.v23i1.14697
Krisnananda, J., & Kartika, A. A. G. (2021). Analisis Kelayakan Ekonomi dan Finansial Pembangunan Jalan Tol Mengwi-Gilimanuk. Jurnal Teknik ITS, 10(2), E253–E258. 10.12962/j23373539.v10i2.69868
Kusuma, S. C. (2017). Analisis Dampak Keterlambatan Pengadaan Tanah Dan Pelaksanaan Konstruksi Terhadap Masa Konsesi Pada Pembangunan Jalan Tol Kertosono-Mojokerto. Institut Teknologi Sepuluh Nopember.
Muna, K. S. (2022). Tinjauan Undang-Undang Nomoar 41 Tahun 2004 Terhadap Tanah Wakaf Terdampak Jalan Tol (Studi Kasus di Desa Baderan Kecamatan Geneng Kabupaten Ngawi). IAIN Ponorogo.
Nurida, M. A. (2018). Identifikasi Dampak Sosial Ekonomi Terhadap Masyarakat Akibat Pembanguanan Jalan Tol Pekanbaru-Dumai. Universitas Islam Riau.
Rani, H. A., & Azlan, M. (2020). Dampak Pembangunan Jalan Tol Banda Aceh-Sigli Terhadap Lingkungan. Tameh: Journal of Civil Engineering, 9(1), 11–21. https://doi.org/10.37598/tameh.v9i1.100
Rara, R. (2022). Analisis Fiqih Siyasah Tentang Mekanisme Ganti Rugi Hak Milik Atas Tanah Dalam Undang-Undang No 2 Tahun 2012 Tentang Pengadaan Tanah Bagi Pembangunan Untuk Kepentingan Umum (Studi Pada Pembangunan BendunganTiga Dihaji Kabupaten OKU Selatan). Universitas Islam Negeri Raden Intan Lampung.
Riyanto, A., & Joesoef, I. E. (2020). Penugasan Badan Usaha Milik Negara Dalam Pengusahaan Jalan Tol: Studi Penugasan PT. Hutama Karya (Persero) Dalam Pengusahaan Jalan Tol Di Sumatera. National Conference on Law Studies (NCOLS), 2(1), 344–379.
Sari, N. F. A., & Widyastuti, H. (2019). Analisis kelayakan ekonomi dan finansial pembangunan jalan tol Pandaan-Malang. Jurnal Teknik ITS, 8(1), E13–E19. 10.12962/j23373539.v8i1.41495
Silalahi, R. N. (2022). Tinjauan Yuridis Proses Pemberian Ganti Kerugian Pengadaan Tanah Bagi Pembangunan untuk Kepentingan Umum dalam Pembangunan Pelabuhan Terminal Multipurpose Kuala Tanjung di Kabupaten Batubara. Universitas Medan Area. https://doi.org/10.34007/jehss.v5i2.1412
Wardana, R. Y. (2021). Masalah Ganti Rugi Lahan Masih Jadi Momok Pembangunan Jalan Tol Sibanceh Seksi 1, Warga Layangkan Protes. Gridoto.Com.
Winodya, V. (2021). Peran Media Sosial Instagram@ Jokowi Dalam Komunikasi Politik Presiden Joko Widodo Saat Peresmian Jalan Tol. Universitas Katholik Soegijapranata Semarang.
Zairi, M. B. (2020). Pembangunan Jalan Tol Sibanceh Masih Terkendala Pembebasan La-han, Pemerintah Aceh Gelar Rakor. Seram-Binews.Com.
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Journal of World Science

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International. that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.